Work out the concrete in round column forms — Sonotube-style footings for deck posts, porch piers, mailbox posts, and pergolas. Enter the tube diameter in inches, how deep each one goes, and how many you are pouring to get total cubic yards, the volume of a single tube, and the 80 lb bag count.

Reviewed by The CostToUpgrade Estimating Desk Last reviewed How we estimate

Your project

Piers

Cardboard forms come in 6, 8, 10, 12, 16 and 18 inch diameters.

Measure hole bottom to the top of the form, including any height above grade.

A typical 12 × 16 ft deck lands on 6–9 piers depending on beam spans.

Pricing

Delivered ready-mix commonly runs $140–$190 per cubic yard before fees.

Estimate

0.7yd³

Concrete needed · All tubes combined — round up when ordering

Volume per tube
3.14ft³
80 lb bags
32bags
Estimated concrete cost
$115.19

Estimates are guidance only and exclude tax, labor, and site conditions unless stated. Confirm with a local pro.

How it's calculated

No black boxes — here is the exact math behind your estimate, so you can check it or adapt it for your own quote.

  1. 1Volume per tube (ft³) = π × (diameter ÷ 24)² × depth
  2. 2Total volume (ft³) = volume per tube × number of tubes
  3. 3Cubic yards = total volume ÷ 27
  4. 4Bags (80 lb) = ⌈ total volume ÷ 0.6 ⌉
  5. 5Cost = cubic yards × price per cubic yard

Worked example

Six 12-inch tube footings for a deck, each poured 4 feet deep.

Inputs

Tube diameter
12 in
Depth of pour
4 ft
Number of tubes
6 tubes
Ready-mix price
165 $/yd³

Result

Concrete needed
0.7 yd³
Volume per tube
3.14 ft³
80 lb bags
32 bags
Estimated concrete cost
$115.19

Tools & materials for this project

As an Amazon Associate we may earn from qualifying purchases, at no extra cost to you.

  • Concrete form tubes Waxed cardboard column forms in 8, 10 and 12 inch diameters.
  • Adjustable post bases Set into wet concrete to keep deck posts up off the pier.
Get real quotes

Compare local pros for concrete tubes

An estimate gets you a budget. A few competing quotes get you the real price. Tell us about the job and we'll help you find vetted contractors nearby.

Get matched

Frequently asked questions

What diameter tube do I need for a deck post?
Eight-inch tubes suit light loads like a small landing or pergola post; 10 and 12 inch are the usual choice under a residential deck post. Size follows the load: the IRC counts 40 psf live plus 10 psf dead, so a post carrying 60 square feet of deck picks up about 3,000 pounds. On 1,500 psf soil that needs 2 square feet of bearing — roughly a 20-inch circle, which is why many decks use a wider pad or flared base under a 12-inch column. This is a planning estimate; footing size is set by local code and your inspector.
How deep should concrete tube footings go?
Deep enough that the bottom bears below the local frost line, and never less than 12 inches below undisturbed ground. Frost depth is effectively zero in south Florida, 18–24 inches across much of the mid-Atlantic, 36 inches in the northern plains, and 42–48 inches in northern Minnesota and New England. Your building department publishes the number for your address — ask before you dig, because a pier that stops short of frost depth will heave and lift the structure over a winter or two. Depth also has to reach undisturbed soil, not backfill.
What about a bell or flared base at the bottom?
A flared footing spreads the load over more soil, which is how a 12-inch column can land on a 20-inch bearing surface. This calculator measures the straight column only, so add the base volume separately. A 20-inch-diameter pad 8 inches thick is about 1.45 cubic feet, or roughly 2.5 additional 80 lb bags per pier. Some regions require the bell instead of allowing a plain column; others prohibit bells in expansive clay because frost can grab the flare. Check the local requirement before you form anything.
Bags or ready-mix for piers?
One cubic yard is 45 80-lb bags. Six 12-inch tubes poured 4 feet deep come to about 0.70 cubic yards — roughly 32 bags, which a rented mixer handles in an afternoon. Past about one cubic yard, or 45 bags, ready-mix usually wins on both cost and consistency once you factor in the short-load fee that most plants charge on orders under 3–4 yards. Bags also let you pour piers one at a time, which matters when holes are scattered around a sloped yard and a truck chute will not reach.
Do the cardboard tubes stay in the ground?
The buried portion stays — it is a form, not a structural element, and it rots away harmlessly. Strip and discard whatever sticks up above grade once the concrete has set, usually the next day, because a wet cardboard collar traps moisture against the pier and looks rough. Score the exposed section with a utility knife and peel it. Set anchor bolts or a galvanized post base into the wet concrete while you pour; posts should never sit directly on soil or in a pocket of the pier.